Haldimand County’s New Administration Building On Track For January 2020 Completion
On October 8, 2019, Haldimand County staff presented Council with an update on the new Administration Building’s construction progress. A number of major construction milestones have been reached and the building is on track to be completed by January 2020.
Painting, floor finishes and light fixture/ceiling tile grid installation is currently underway within the building’s interior. Electrical work will continue over the next several weeks, as will landscaping and work on remaining exterior finishes (e.g: composite paneling, landscaping). Furniture deliveries and the overall setup/configuration of the building’s interior will begin in early December. Staff moves and satellite office closures are expected to begin in January 2020.
All services currently available at the County’s satellite offices will be offered at the new administration building, and new online tools will be introduced to provide more 24/7 services to residents. Library branches will be retrofitted with ‘Community Hubs’ – computer and information stations designed to connect resident with County news & online services. Library staff will be available to provide instruction and guidance on how to make use of online services, like how to pay taxes or water bills online.
Satellite office closure information will be announced and communicated to residents later this fall. To ensure service consistency across the County, Community Hubs openings will be coordinated to occur prior to satellite office closures.
The project is within budget and moving along well to substantial completion despite weather delays and impacts related to trades-related workforce disruptions in spring 2019.
More information about the new Central Administration Building – including construction updates – will be shared on the County website and social media channels as the project progresses.